U.S. Highway 165 South Lighting Project Groundbreaking
Mayor Jamie Mayo, the Monroe City Council, and local LaDOTD officials invite the media to the following:
EVENT: U.S. Highway 165 South Lighting Project Groundbreaking
TIME/DATE: 10 am Thursday, October 17, 2019
LOCATION: Monroe Public Safety Center, 1810 Martin Luther King, Jr. Drive (U.S. Hwy 165 South).
SUMMARY: This estimated $551,244 project will install approximately thirty-eight (38) new street lighting poles on U.S. Highway 165 South from Century Boulevard to Winnsboro Road. The project engineer is Lazenby & Associates. The contractor is Ernest P. Breaux Electrical, LLC. The project is expected to be completed in 90 working days. The project is 20% funded through City of Monroe Capital Infrastructure Funds and 80% funded through LaDOTD Urban Systems Funds.