Notice of Hearing/Ordinance - Hear complaints about the proposed 5 year Capital Improvement Plan

NOTICE

NOTICE IS HEREBY GIVEN that a Public Hearing will be held by the City Council of the City of Monroe, Louisiana, at its regular meeting place, the Council Chamber, City Hall Building, Monroe, Louisiana, Tuesday, April 12, 2022, beginning at 6:00 p.m., to hear and consider all comments, protests and objections relative to the following proposed 5 year Capital Improvement Plan for the City of Monroe.

 

FIVE YEAR CAPITAL IMPROVEMENT PLAN

              

 

FOR THE FIVE YEARS ENDED APRIL 30, 2027

              

 

PREPARED FOR BUDGET YEAR 2023

              

 

       

FOR THE YEAR ENDED  APRIL 30,

     

PROJECT

 

RESPONSIBLE

TOTAL

           

 

NAME

 

DEPARTMENT

COST

 

2023

 

2024

 

2025

 

2026

 

2027

 

 

Street Improvements

               

 

 

Maintenance

 

Public Works (PW)

 On going

 

$1,500,000

 

$1,500,000

 

$1,500,000

 

$1,500,000

 

$1,500,000

 

 

 

Hwy. 165 Connector - Phase I

Eng

 

$3,580,000

    

 

  

2,000,000

 

1,500,000

 

 

 

Bridge Replace/Rehab/Repair-Multi/Sites

Eng

 

5,600,000

 

1,300,000

         

 

 

Various overlay project

  

4,300,000

 

1,000,000

 

2,000,000

 

1,000,000

     

 

   

Total Street Proj.

13,480,000

 

3,800,000

 

3,500,000

 

2,500,000

 

3,500,000

 

3,000,000

 

 

                 

 

Sewer Improvements

               

 

 

Citywide I&I study

   

450,000

 

200,000

 

250,000

       

 

 

Close Oxidation Pond at MLU

  

1,000,000

 

200,000

 

800,000

       

 

 

Rehab trunk lines to reduce I&I

  

2,000,000

 

100,000

 

900,000

 

1,000,000

     

 

 

Equalization Basin Rehab

Eng/PW

 

4,000,000

 

500,000

 

2,000,000

 

1,500,000

     

 

   

Total Sewer Proj.

7,450,000

 

1,000,000

 

3,950,000

 

2,500,000

 

0

 

0

 

 

                 

 

Drainage Improvements

               

 

 

Georgia St. PS/Parker Ditch - Statewide Flood Program(SFP)

Eng/PW

 

5,430,000

 

200,000

 

2,700,000

 

2,230,000

     

 

 

Calypso PS

 

Eng/PW

 

2,900,000

 

50,000

 

150,000

 

300,000

 

1,400,000

 

1,000,000

 

 

 

Oregon Trail protection levee

Eng/PW

 

1,500,000

 

450,000

 

1,000,000

       

 

 

Youngs Bayou Retention

Eng/PW

 

6,867,000

 

200,000

 

600,000

 

2,000,000

 

2,000,000

 

2,000,000

 

 

   

Total Drainage Proj.

16,697,000

 

900,000

 

4,450,000

 

4,530,000

 

3,400,000

 

3,000,000

 

 

                 

 

Water Improvements

               

 

 

Hwy 165 Tank & Main

 PW

 

4,370,000

           

 

 

Treatment Plant Expansion & Renovation 

 PW

 

45,000,000

 

20,000,000

 

20,000,000

 

5,000,000

     

 

 

Water Distribution System Improvements

  

17,000,000

 

750,000

 

750,000

 

750,000

 

750,000

 

750,000

 

 

   

Total Water Proj.

66,370,000

 

20,750,000

 

20,750,000

 

5,750,000

 

750,000

 

750,000

 

 

                 

 

Fire Improvements

               

 

 

5 new pumper trucks

Fire

 

2,600,000

 

150,000

 

1,225,000

 

1,225,000

     

 

   

Total Fire Proj.

2,600,000

 

150,000

 

1,225,000

 

1,225,000

 

0

 

0

 

 

                 

 

Sidewalk & lighting projects

               

 

 

Enhance Gr - DeSiard

 Eng/PW

 

750,000

 

500,000

 

250,000

       

 

 

Enhance Gr - Ph 2 Louisville

 Eng/PW

 

1,698,000

   

698,000

 

500,000

 

500,000

   

 

 

Enhance Gr - Jackson St

 Eng/PW

 

1,022,200

 

1,022,200

         

 

 

Enhance Gr - Winnsboro Rd

 Eng/PW

 

1,022,200

 

522,200

 

500,000

       

 

   

Total Capital Proj.

4,492,400

 

2,044,400

 

1,448,000

 

500,000

 

500,000

 

0

 

 

                 

 

Airport Projects

               

 

                 

 

 

Runway Extension

 

Airport

 

8,000,000

 

1,600,000

 

1,600,000

 

1,600,000

 

1,200,000

   

 

 

Taxiway Realignment

Airport

 

12,000,000

 

2,400,000

 

2,400,000

 

2,400,000

 

2,400,000

 

2,000,000

 

 

   

Total Airport Proj.

20,000,000

 

4,000,000

 

4,000,000

 

4,000,000

 

3,600,000

 

2,000,000

 

 

                 

 

I-20

                

 

 

I-20/Garrett - Kansas Connector

Eng

 

35,000,000

 

1,500,000

 

3,500,000

 

10,000,000

 

10,000,000

 

9,000,000

 

 

 

Kansas Lane Connector

Eng

 

30,000,000

 

6,000,000

 

10,000,000

 

8,000,000

 

800,000

   

 

 

Frontage Road Projects

I-20

 

13,500,000

 

3,000,000

 

3,000,000

 

2,000,000

 

1,260,000

   

 

   

Total I-20 Proj.

78,500,000

 

10,500,000

 

16,500,000

 

20,000,000

 

12,060,000

 

9,000,000

 

 

                 

 

   

Total for all Projects

 

$209,589,400

 

$43,144,400

 

$55,823,000

 

$41,005,000

 

$23,810,000

 

$17,750,000

 

 

     

 

           

 

                      

NOTICE IS FURTHER GIVEN that copies of the proposed Capital Improvement Program is on file in the City Clerk’s Office, 2nd floor, City Hall Building and can be examined by the public during regular business hours Monday through Friday.

 

All persons who wished to comment, protest or object to any portion of the above mentioned proposed program is urged to attend this meeting.

 

NOTICE PUBLISHED IN THE MONROE NEWS-STAR ON MARCH 25TH & APRIL 1ST, 2022.

 

CAROLUS S. RILEY,CMC,MMC

City Clerk