WHAT: Davis Drive Drainage Improvement Project Groundbreaking
WHEN & WHERE: 10:00 am Thursday, August 15, 2019, @ the intersection of Jason Drive
and Memorial Drive in the King Oaks Subdivision in Monroe
PROJECT SUMMARY: We will construct drainage improvements by replacing an estimated
718 linear feet of existing deteriorated drainage pipe and four (4) catch basins. This improvement
will help move water on Davis Drive to Jason Drive across memorial Drive and into an open
drainage canal. The estimated cost is $226,885. The design engineer is Denmon Engineering
and the project contractor is CW&W Contractors, Inc. The contract calls for the project to be
completed in 90 days.